SCADA Replacement / DMS Planning - MAGIC VALLEY ELECTRIC CO-OP
  • SCADA Replacement & Additional Requirements:
    • Replacement of Existing QEI Dual Redundant Master Servers w/ OpenVMS OS, Dual Operator Workstations, Terminal Servers, DNP3 Serial (Client & Server) Protocol to existing RTU's
    • Attention to Comprehensive Security & Compliance with NERC/CIP
    • Backhaul Communication Capability to include: Cellular; Frame Relay; Fiber; Licensed/Unlicensed RF; & MPLS
    • Additions: DNP3 WAN/LAN (Client & Server) Protocol for new Distribution Automation (DA) Deployment; MultiSpeak Interface; Secure Web Server for Remote Access; & DMS Scalability for Future Phases
  • Amato Consulting Support Services & Project Status -
    • July 2012 - Work with SCADA staff to Inventory all SCADA existing Master Server related equipment, Software, & System Points. Also, identify additional desired technical requirements & capabilities for replacement system.
    • Prepare detailed RFQ package to obtain system offerings that meet all requirements of owner as well as provide for "apples to apples" comparison
    • Obtain list of qualified SCADA vendors and work with SCADA staff to short list invitees.
    • Coordinate Vendor Interviews & Demonstrations.
    • Arrange potential visits of existing deployments.
    • August 2012 - Send RFQ packages for Responsive Vendor Bid Submittals.
    • November 2012 - Perform detailed Bid Analysis with Existing Customer Interviews & Submit Recommendation
    • January 2013 - Award to OSI after Owner's Board approval. Deployment Plan Sequenced & Contract Finalized
    • February 2013 - OSI/MVEC Project Kickoff Meeting